Surian Residences
Apartment with Condo Facilities in Kota Kinabalu, Sabah
Welcome to the newly launch RDS Bina website. We are proud to present you this website that contains many of our company information.

You can find the details of our key personnel, portfolios, and more importantly, what we do best in this website.
Suri Puteri - Shop office and Service Apartment, Shah Alam

Proposed Building Works for Pembangunan Bercampur Yang Mengadungi Kedai Pejabat 68Unit (3-8 tingkat), Kebuk Sampah (2 unit), Pangsapuri Perkhidmatan 352unit (15 tingkat), Kemudahan Rumah Kelab (tingkat bawah), Tempat Letak Kerata Di Tingkat Basement (2 Tingkat), Rumah Pengawal (1 Unit) Di Atas Lot 48, Jalan Rama-rama 20/2, Seksyen 20, 40300 Shah Alam. 2009-Main Contractor

Developer : Semangat Ulung Sdn. Bhd.
Architect : HSMK Associates Sdn. Bhd.
Contract Period : Section A: Shop Office (15months); Section B: Apartment (27 months)
Commencement Date : 1st October 2009
Completion Date : Section A: 31st December 2010; Section B: 1st November 2011
Kingfisher Sulaman, Menggatal, Kota Kinabalu

Proposed Building and Infrastructure Works For The Housing Development on CL. 015046607 Off Jalan Sulaman, Menggatal, Kota Kinabalu, Sabah Phase 5A (K0203 - Package F) 40 Units of 2 1/2 Storey Detached House, 1 Unit Guard House and Infrastructure Works - 2009-Main Contractor.

Proposed Mixed Development on CL. 015046607 at Menggatal, Kota Kinabalu with Strata Title For the 4 & 5 Storey Shop / Office Block - (Phase 5B) - 2010 - Main Contractor.

Developer : Hap Seng Properties Development Sdn. Bhd.
SO : Corporated International Consultants
Contract Period : 22 Months, 15 Months
Commencement Date : 13th July, 2009; 3rd May 2010
Completion Date : 5th May 2011; 5th September 2011
Saujana Emas - 66 Units of Semi-D House & Infrastructure Works, Kajang

(Parcel 1: 2 Units of Semi-Detached House type A and Infrastructure Works) Proposed Housing Development on Lot 1799, Mukim Kajang, Daerah Hulu Langat, Selangor Darul Ehsan - 2008, Main Contractor.

(Parcel 2) Proposed Housing Development Comprising of 62 Units of 2 Storey Semi-Detached House Type A, 2 Units of 2 Storey Semi-Detached Type B, 1 Unit of TNB Substation and Infrastructure Works on Lot 1799, Mukim Kajang, Daeraf Hulu Langat, Selangor Darul Ehsan - 2009, Main Contractor.

Developer : Tanming Ventures Sdn. Bhd.
Architect : Arkitek CKL
Contract Period : 5 Months; 16 Months
Commencement Date : 14th November, 2008; 4th June, 2009
Completion Date : 15th May 2009; 25th January 2011
Prima Sri Gombak, Bandar Selayang

Building Works For the Proposed Commercial Development on Lot 10228 and Lot 34479, Daerah Gombak, Bandar Selayang, Selangor Darul Ehsan - 2008, Main Contractor

Developer : BH Builder Sdn. Bhd.
Architect : Perkhidmatan Arkitek
Contract Period : 16 Months
Commencement Date : 2nd September, 2008
Completion Date : 24th May 2010
Taming Mutiara - 142 Units of 3 Storey Semi-D & 6 Units Bungalow at Sg. Long

4 Units of 3 Storey of Semi-Detached (Type A & Type B) On Lot 4156, Mukim Cheras, Daerah Hulu Langat, Selangor Darul Ehsan For M/S Taming Management Sdn Bhd. - 2006.

58 Units of 3 Storey of Semi-Detatched House (Type A-48 Units & Type B-10Units), 4 Units of Bungalow House, 1 TNB Sub-Station and Infrastructure Work on Lot No. 4156, Mukim Cheras, Daerah Hulu Langat, Selangor - 2007 Main Contractor.

(Parcel 2) 66 Units of 3 Storey of Semi-Detatched House Type A, 14 Units Of Semi-Detached House Type B, 2 Units of Bungalow House, 1 Units of TNB Sub-Station and Infrastructure Work on Lot No. 4156, Mukim Cheras, Daerah Hulu Langat, Selangor - 2008 Main Contractor.

Developer : Tanming Ventures Sdn. Bhd.
Architect : Paradigm Architects Sdn. Bhd.
Contract Period : 15 Months; 18 Months
Commencement Date : 1st December 2007; 15th October 2008
Completion Date : 21st July 2009; 3rd September 2010
Ritamix Factory, Shah Alam

Cadangan Membina Sebuah Kilang/Gudang 1 Tingkat Berserta 2 Tingkat Mezzanine, 1 Unit Menara Memproses, Pejabat 3 Tingkat & 1 Unit Pondok Pengawal Beralamat Ritamix Sdn Bhd, No. 1, Jalan Sapir 33/7, Lot PT 43471, Premier Industrial Park, Seksyen 33, 40350 Shah Alam, Selangor Darul Ehsan.

Developer : Ritamix Sdn. Bhd.
Architect : Paradigm Architects Sdn. Bhd.
Contract Period : 4 ½ Months
Commencement Date : 15th December 2009
Completion Date : 15th August 2010
Karamunsing Capital Kota Kinabalu

55 Lots of Shops/Offices, 1 Level Rooftop Carpark and Associated External Works & Infrastructures at Karamunsing, Off Jalan Tuaran, Kota Kinabalu, Sabah -2007, Main Contractor.

Developer : Syarikat Kapasi Sdn. Bhd.
Architect : Arkitek Billings Leong & Tan Sdn. Bhd.
Contract Period : 18 Months
Commencement Date : 1st August, 2007
Completion Date : 30th April 2009
Aman Puri Shop Office

19 units of 2 Storey Shop Office complete with an open carpark at Mukim Batu, Daerah Gombak, Majlis Perbandaran Selayang, Selangor Darul Ehsan for Tetuan Suri Puri Sdn Bhd - Main Contractor.

Developer : Suri Puri Sdn Bhd
Architect : Perkhidmatan Akitek
Contract Period : 12 Months
Commencement Date : 29th October, 2007
Completion Date : 8th October, 2008 ( 1 month early completion)
Taman Selaseh - 2 Storey Terrace House

30 Units of Double Storey Terrace House on Lot 45153, 45155 & 45156, Taman Selaseh, Mukim Batu, Daerah Gombak, Selangor Darul Ehsan. - 2007-Main Contractor.

Developer : Evergreen Supplies Sdn Bhd
Architect : Perkhidmatan Akitek
Contract Period : 16 Months
Commencement Date : 13th June, 2007
Completion Date : 20th August, 2008 (2 months early completion)
Taman Seri Minang - 2 ½ Storey Semi-Detached Houses & 2 ½ Storey Terrace house, Cheras

2 Units of sample house on Lot 2831, Mukim Cheras, Daerah Cheras, Selangor Darul Ehsan -2006 -Main Contractor.

14 units 2 ½ storey semi-detached houses, 60 units 2 ½ storey terrace house and infrastructure works on lot 2831, Mukim Cheras, daerah Hulu Langat, Selangor Darul Ehsan -2006

Developer : Tanming Bhd
Architect : Asima Architects Sdn. Bhd
Contract Period : 15 Months
Commencement Date : 15th September, 2006
Completion Date : 27th May, 2008
Taman Ulg Bungalow, Hulu Langat

123 units Bungalow Type A, A1, B, C, C1, C2, C2A, D, D1, E, E1, F &H And 2 Units TNB Sub-station on Lot 4261, 4262, 4264 & 1447 Mukim Hulu Langat And Lots 2181 & 2182, Mukim Cheras, Daerah Hulu Langat, Selangor Darul Ehsan For Spring Court Sdn Bhd. - 2007-Main Contractor.

Developer : OCH / Spring Court Sdn. Bhd.
Architect : Akipraktis
Contract Period : 7 Months
Commencement Date : 26th April, 2006
Completion Date : 31st March, 2007
KK Times Square Sabah

72 Lots of Building Blocks and Basement at Coastal Highway, Kota Kinabalu, Sabah (KK Times Square Phase I) - 2006-Main Contractor.

Developer : Syarikat Kapasi Sdn. Bhd.
Architect : Arkitek Billings Leong & Tan Sdn. Bhd.
Contract Period : 22 Months
Commencement Date : 15th December, 2005
Completion Date : 15th January, 2008
Taman Bukit Serdang - 2 Storey Semi-Detached

2 units 2 Storey Semi-Detached show house at Taman Bukit Serdang - 2005

26 units of 2 Storey Semi-Detached at Taman Bukit Serdang - 2005

Developer : Casa Serdang Sdn. Bhd.
Architect : HMSK Associates Sdn. Bhd.
Contract Period : 18 Months
Commencement Date : 19th October, 2005
Completion Date : 7th December, 2006 (4 months early completion)
Saujana Gombak - Shop Lots, Low Cost Apartment & Medium Cost Apartment.

22 Units 3 Storey Shop Office at Sri Gombak, Selayang - 2005- Main Contractor

320 units of Medium Cost Apartment & 80 units of Low Cost Apartment at Sri Gombak, Selayang - 2005 - Main Contractor.

Infrastructure Works for 22 Units 3 Storey Shop Office, 320 units of Medium Cost Apartment & 80 units of Low Cost Apartment at Sri Gombak, Selayang.

Developer : Sureman Properties Sdn. Bhd.
Architect : Md. Ayof Consultant Architect
Contract Period : 15 Months & 20 Months
Commencement Date : 1st April, 2005 & 10th May, 2005
Completion Date : 26th February 2007 & 4th October 2007
Sutera Bukit Tunku Condominium

24 Units 4 storey Condominium, penthouse and 1 basement, swimming pool at Bukit Tunku 2004-Main Contractor.

Developer : Taman Bestari Sdn. Bhd.
Architect : DP Architects Sdn. Bhd.
Contract Period : 16 Months
Commencement Date : 2nd November, 2004
Completion Date : 31st October, 2006
Kota Kemuning Bungalow (Phase RP 5-PH3A)

Section 31, Bandar Kota Kemuning, Shah Alam, Selangor - 27 Units 2 Storey Bungalow, Fasa RP5 (Phase 3A) (Hicom-Gamuda Project); 2004 - Main Contractor.

Developer : Hicom Gamuda Development Sdn. Bhd.
Architect : A&A Architects Sdn. Bhd.
Contract Period : 16 Months
Commencement Date : 17th June, 2004
Completion Date : 16th October, 2005
Dynasty 3 - Shop Office

Earth Works, Piling, Pilecaps and Column Starter Bars at Jalan Kuchai Lama - 81 Unit 2 Storey and 71 Unit 3 Storey Shop Office -2004-Main Contractor.

152 Units Shop Office at Jalan Kuchai Lama - 81 Unit 2 Storey and 71 Unit 3 Storey Shop Office - 2004-Main Contractor.

Developer : South Malaysia Industries Bhd.
Architect : SA Architects Sdn. Bhd.
Contract Period : 6 Months & 16 Months
Commencement Date : 29th March, 2004
Completion Date : 21st March, 2006
Kota Kemuning Semi-Detached House (Phase 5)

Section 31, Bandar Kota Kemuning, Shah Alam, Selangor - 12 Units Semi-Detached House, Fasa RP5 (Phase 1D) (Hicom-Gamuda Project); 2004 - Main Contractor.

Developer : Hicom Gamuda Development Sdn. Bhd.
Architect : Garis Architect
Contract Period : 14 Months
Commencement Date : 5th April, 2004
Completion Date : 10th March, 2005 (3 months early completion)
Taman Bkt Serdang - 61 Units 2 Storey & 12 Units 2 ½ Storey Link House

2 Units of Double Storey Terrace House at Serdang (Sample House); 2003 - Main Contractor

Taman Bukit Serdang - 38 Units 2 Storey Terrace House (Type A), 28 Units 2 Storey Terrace House (Type B), 12 Units 2 ½ Storey Terrace House; 2003 - Main Contractor

Developer : Tanigra Construction Sdn. Bhd.
Architect : Arkitek OBS
Contract Period : 14 Months
Commencement Date : 13th August, 2003
Completion Date : 15th October, 2004 (2 Months early completion)
Tmn Bkt Serdang - 33 Units 2 ½ Storey Link House & 10 Units Semi-Detached

33 Units 2 ½Storey Terrace House & 10 Units Double Storey Semi-detached House at Serdang; 2003 - Main Contractor.

Developer : Tanigra Construction Sdn. Bhd.
Architect : Arkitek OBS
Contract Period : 14 Months
Commencement Date : 17th March, 2003
Completion Date : 30th April, 2004 ( I month early completion )
Bandar Botanic

Bandar Botanic Township, Klang (Gamuda Project) - 34 Units Double Storey Semi-Detached House (Phase 2A2); 2002 - Main Contractor.
Commercial 4, Bandar Botanic -40 Unit {20 unit (22x80) & 20 Unit (22x75)} 3 Storey Shop Office at Bandar Botanic; 2005 - Main Contractor
Bandar Botanic Township, Klang (Gamuda Project) - 52 Units Double Storey Semi-Detached House (Phase 2B2); 2002 - Main Contractor

Developer : Harum Intisari Sdn. Bhd.
Architect : GLC Architect | Garis Architect | Atelier ADT Akitek Sdn Bhd
Contract Period : 13 Months | 14 Months | 13 Months
Commencement Date : 17th July, 2002 | 15th September, 2003 | 19th July, 2002
Completion Date : 15th January, 2004 | 13th January, 2005 | 15th January, 2004
Kota Kemuning - Super Link House (Phase RP3K)

Section 31, Bandar Kota Kemuning, Shah Alam, Selangor - 47 Units Double Storey House (Hicom-Gamuda Project); 2002 - Main Contractor.

Developer : Hicom Gamuda Development Sdn. Bhd.
Architect : GLC Architect
Contract Period : 16 Months
Commencement Date : 20th May, 2002
Completion Date : 19th September, 2003
Valencia - Bungalows Phase 1C & Phase 1 F

Valencia, Sg. Buloh (Gamuda Project) - 23 Units of Bungalow House (Phase 1C); 2002 - Main contractor.

Valencia, Sg. Buloh (Gamuda Project) - 19 Units of Bungalow House (Phase 1F); 2002 - Main contractor

Developer : Gamuda Engineering Sdn. Bhd.
Architect : Sixone Architect Sdn Bhd, Veritas Architect Sdn. Bhd.
Contract Period : 14 Months (each phase)
Commencement Date : 10th April, 2002
Completion Date : 25th February, 2004; 4th February 2004
Chong Hwa School

Chong Hwa School, Jalan Pahang - 4 ½ Floor Building; 2002 - Main Contractor.

Developer : SJK (C) Chong Hwa
Architect : Singma Jurutera-Jurutera Perunding
Contract Period : 13 Months
Commencement Date : 1st March, 2002
Completion Date : 30th April, 2003
Hong Leong Group Projetcs

Taman Bukit Rahman Putra, Sg Buloh (Hong Leong Group Project) 24 Units Single Storey Shophouses; 1999
Pantai Sepang Putra, Mukim Sepang (Hong Leong Group Project) 77 Units Single Storey Bungalow (Phase 2B1); 1999
Bukit Rahman Putra, Sg Buloh, Mukim Rawang (Hong Leong Group Project) 41 Units Double Storey Link House; 2001

Developer : Hong Leong Group
Architect : Barisan Architect | Arkitek Teknikarya | Damansara Architect
Contract Period : 10 Months | 12 Months | 12 Months
Commencement Date : 1st June, 1999 | 16th November, 1999 | 28th March, 2001
Completion Date : 31st March, 2000 | 1st December, 2000 | 4th June, 2002